2.9 Chronology of the ISO Mission

March 1979 Proposal to ESA for ISO
1979 Assessment Study
1980 Pre-Phase-A Study
1981-1982 Phase-A Study
March 1983 Selection of ISO for inclusion in ESA Scientific Programme
July 1984 Call for Experiment and Mission Scientist Proposals
June 1985 Selection of Scientific Instruments
December 1986 Start of Phase-B (Definition)
March 1988 Start of Phase-C/D (Main development)
April 1994 Call for Observing Proposals
17 November 1995 Launch
21 November 1995 Start of Commissioning Phase
9 December 1995 Start of Performance Verification Phase
4 February 1996 Start of Routine Phase
August 1996 Supplemental Call for Observing Proposals
February-July 1998 Transition Phase to Post-Operations
8 April 1998 Helium boil-off / End of Routine Phase
16 May 1998 Termination of satellite communication
9 December 1998 Opening of the ISO Data Archive
August 1998-December 2001 Post-Operations Phase
28 February 2002 Release of the ISO Legacy Archive
January 2002-December 2006 Active Archive Phase